There is a Power cut in the area around our Avro Court (Huntingdon) Data Centre.
Power to the data centre is currently being maintained by our UPS and generator on site
UK Power Networks are working to restore the mains power to the area. In the mean time power should be considered at risk, However our UPS and Generator are working currently so there should be no issues.
Mains Power was restored just after 23:30 we are monitoring but have switched back from Generator to mains power for now.