One of our interconnects in Manchester may see temporary up-ticks in latency and longer routing choices because of the work planned below. This will not affect connectivity and will revert to normal after the work window has closed.

Service Affected:
Level3 Transit, Manchester Bearer

Start of maintenance:
25/10/2016 – 00:01 GMT

End of maintenance:
25/10/2016 – 03:00 GMT

Duration of work:
Up to one hour within stated window

Impact of work:
Outage / Disruption to services

Classification of works:
Repair / Planned (Third Party)

Description of works:
Level 3 Communications will implement scheduled maintenance to perform upgrade work on core network equipment to free up memory and prevent future service interruptions to customer services.