Following on from the switch replacement in London Harbour Exchange square recently the vendor had advised us of a potential fan issue on the switch supplier and have supplied is with a second replacement switch,

We will swap this switch (again) on Saturday evening to ensure that all fans etc are fully working

While we have allowed a four how window here we expect the outage to be no longer than 10-20 minutes all being well.The new switch is all pre-configured so this is a simple chassis swap

We apologise for the extra work here but we would prefer to ensure there’s no potential unplanned issue here

This work was completed at 22:16 on Saturday with an outage of less than 10 minutes